News

2010/02/05 - Studio operational

Photographic studio

2009/02/27 - Studio construction: Mezzanine floor completed

The office area mezzanine floor and staircase has been completed.

Mezzanine floor
Builing mezzanine floor

2008/12/15 - Studio construction: Outside completed

Building

The main construction work and exterior of the building has been completed.

2008/09/22 - Studio construction: Walls completed

Studio walls

Due to all the rain we have had the last few weeks, construction has been going at a snail's pace. Despite this, the walls have been completed and now stand the full 5 meters high.

In the next few days construction of the roof will begin.

2008/09/05 - Studio construction: Construction of walls up to 3m level

Studio walls

The walls are now 3 meters high - another 2 meters to go.

2008/08/22 - Studio construction: Construction at floor level

Studio floor

Foundations and floor has been cast.

Foundations: 19 tons of concrete
Floor: 16 tons of concrete

2008/08/01 - Studio construction: Start of construction

Start of construction

Construction has started.

2008/07/03 - Studio construction: Plans approval

Plans

Today we finally got approval for the construction of our new studio. The new studio will consist of a double volume main studio with upstairs office area.