News
2010/02/05 - Studio operational

2009/02/27 - Studio construction: Mezzanine floor completed
The office area mezzanine floor and staircase has been completed.


2008/12/15 - Studio construction: Outside completed

The main construction work and exterior of the building has been completed.
2008/09/22 - Studio construction: Walls completed

Due to all the rain we have had the last few weeks, construction has been going at a snail's pace. Despite this, the walls have been completed and now stand the full 5 meters high.
In the next few days construction of the roof will begin.
2008/09/05 - Studio construction: Construction of walls up to 3m level

The walls are now 3 meters high - another 2 meters to go.
2008/08/22 - Studio construction: Construction at floor level

Foundations and floor has been cast.
Foundations: 19 tons of concrete
Floor: 16 tons of concrete
2008/08/01 - Studio construction: Start of construction

Construction has started.
2008/07/03 - Studio construction: Plans approval

Today we finally got approval for the construction of our new studio. The new studio will consist of a double volume main studio with upstairs office area.